Explosives Regulations, 2013 (SOR/2013-211)

Regulations are current to 2017-12-11 and last amended on 2016-04-15. Previous Versions

Marginal note:Operating procedures
  •  (1) Operating procedures, including procedures to minimize the likelihood of an ignition, must be put in place for every manufacturing operation to be carried out in a mobile process unit.

  • Marginal note:Copy

    (2) A copy of the operating procedures for each mobile process unit must be kept in the unit and must be made available to workers.

Marginal note:Process unit records
  •  (1) A record must be made for each period during which a mobile process unit operates. The record must be kept for two years after the date on which it is made and must include the following information:

    • (a) the dates on which the period of its operation began and ended;

    • (b) a short description of the Footnote *explosives manufactured during the period and of their properties;

    • (c) the quantity of explosives manufactured; and

    • (d) the maintenance of and repairs to the unit, the dates on which the work was carried out and the name of the person who did the work.

  • Marginal note:Decontamination records

    (2) A record must be made for each Footnote *decontamination of equipment that is used in a mobile process unit. The record must describe the contamination and the means of decontamination and include the names of the workers who carried out the decontamination and the name of the supervisor who inspected the equipment after the decontamination. The record must be kept for two years after the date on which the equipment is disposed of.

Marginal note:Maintenance
  •  (1) Every mobile process unit must be maintained in good operating condition.

  • Marginal note:Servicing during use

    (2) Minor servicing of a mobile process unit may be done while it is in use if the following requirements are met:

    • (a) the servicing is routine and integral to the use of the unit; and

    • (b) the servicing is done by a competent person.

  • Marginal note:Work permit

    (3) All other maintenance or repair work, if it is done at the factory, must be carried out by a competent person who has been issued a work permit by the licence holder.

  • Marginal note:Contents of work permit

    (4) A work permit must set out the procedures to be followed during the maintenance or repair work and the measures that must be taken before, during and after the work to eliminate any possibility of an ignition.

  • Marginal note:Decontamination

    (5) A mobile process unit must be Footnote *decontaminated at the factory before it is taken outside the factory for maintenance or repair.

  • Marginal note:Work done outside factory

    (6) If maintenance or repair work is done outside the factory on manufacturing equipment that is in or on a mobile process unit and whose malfunction could increase the likelihood of an ignition (for example, pumps or safety trips), it must be done by a competent person.

  • Marginal note:Repairs at site of breakdown

    (7) In the case of a mechanical breakdown of a vehicle used as a mobile process unit, repairs to the vehicle may be done at the location of the breakdown only if doing the repair work will not increase the likelihood of an ignition and the work is done by a competent person.

  • Marginal note:Unloading and towing

    (8) If doing the repair work could increase the likelihood of ignition, the unit must be towed to the factory for repair.

  • Marginal note:Logbook and work permits

    (9) A logbook of all maintenance and repair work done to a mobile process unit, or to any manufacturing equipment in or on the unit whose malfunction could increase the likelihood of an ignition, must be kept for two years after the date on which the last entry is made. The work permits for the maintenance and repair work must also be kept for two years after the date on which the work is completed. The logbook and permits must be kept at the factory.

  • Marginal note:Progressive cavity pump logbook

    (10) For each progressive cavity pump, a separate logbook that sets out the operating history of the pump and the maintenance and repair work done to it must be kept at the factory for the life of the pump.

Marginal note:Use at client site
  •  (1) A mobile process unit may be used to Footnote *manufacture Footnote *explosives at a client site, but only if the unit and the site are both specified in the division 1 factory licence or satellite site certificate.

  • Marginal note:Manufacturing operations

    (2) All manufacturing operations at a client site must be carried out by a competent person.

  • Marginal note:Precautions

    (3) Before manufacturing operations begin, every one at the client site must be informed of the precautions that must be taken while dewatering, driving over loaded boreholes, handling charging hose and carrying out charging operations.

  • Marginal note:Hazards

    (4) Any thing or activity that could increase the likelihood of an accidental ignition must not be allowed within 15 m of a mobile process unit and its charging hose.

  • Marginal note:Performance-diminishing substance

    (5) A person must not be permitted to be within 15 m of a mobile process unit and its charging hose while the unit is operating if there are reasonable grounds to believe that the person is under the influence of or is carrying alcohol or another performance-diminishing substance. A person who has taken a prescription drug may be permitted to enter the area if they have medical proof that the drug is needed and will not impede their ability to function safely.

  • Marginal note:No smoking

    (6) A person must not be permitted to smoke within 15 m of a mobile process unit and its charging hose.

  • Marginal note:Thunderstorms

    (7) On the approach of a thunderstorm, if a mobile process unit is at the surface at a client site, all manufacturing operations in the unit must be shut down and all people in the vicinity of the unit must be immediately moved to a safe place. Until the storm passes, the operations must remain shut down and the people must not be permitted to return to the vicinity of the unit.

Marginal note:Packaging at satellite or client site
  •  (1) Blasting explosives in bulk that are manufactured in a mobile process unit may be packaged at a satellite or client site, but only if the explosives

    • (a) have been removed to prepare the unit for cleaning or Footnote *decontamination;

    • (b) are to be used as samples for laboratory analysis;

    • (c) have been used to calibrate the process equipment;

    • (d) are to be used to charge boreholes that the unit cannot access during its operations at a client site; or

    • (e) are to be used to charge boreholes that present unforeseen conditions rendering their use unsafe if they are left unpackaged.

  • Marginal note:Packaging

    (2) The packaging must prevent the explosives from leaking or spilling and minimize the likelihood of an accidental ignition.

SUBDIVISION dRequirements for Workers, Visitors and Other People

Factory and Satellite Site

Marginal note:Authorization to enter
  •  (1) Before entering a factory or satellite site, every worker who is not an employee and every visitor must obtain the authorization of the holder of the division 1 factory licence. A visitor must be at least 17 years old.

  • Marginal note:Visitors

    (2) While at a factory or satellite site, a visitor must remain under the supervision of a competent person.

  • Marginal note:Performance-diminishing substance

    (3) A worker or visitor who is under the influence of or is carrying alcohol or another performance-diminishing substance must not enter a factory or satellite site. However, a worker or visitor who has taken a prescription drug may enter if they have medical proof that they need the drug and that it will not impede their ability to carry out their functions or to visit safely.

 
Date modified: