Reduction of Carbon Dioxide Emissions from Coal-fired Generation of Electricity Regulations (SOR/2012-167)

Regulations are current to 2024-11-26 and last amended on 2018-11-30. Previous Versions

Marginal note:Definitions

  •  (1) The following definitions apply in these Regulations.

    Act

    Act means the Canadian Environmental Protection Act, 1999. (Loi)

    ASTM

    ASTM means ASTM International, formerly known as the American Society for Testing and Materials. (ASTM)

    auditor

    auditor means a person who

    • (a) is independent of the responsible person who is to be audited; and

    • (b) has demonstrated knowledge of and experience in

      • (i) the certification, operation and relative accuracy test audit (RATA) of continuous emission monitoring systems, and

      • (ii) quality assurance and quality control procedures in relation to those systems. (vérificateur)

    authorized official

    authorized official means

    • (a) in respect of a responsible person that is a corporation, an officer of the corporation who is authorized to act on its behalf;

    • (b) in respect of a responsible person that is an individual, that person or a person authorized to act on that individual’s behalf; and

    • (c) in respect of a responsible person that is another entity, a person authorized to act on that other entity’s behalf. (agent autorisé)

    biomass

    biomass means a fuel that consists only of non-fossilized, biodegradable organic material that originates from plants or animals but does not come from a geological formation, and includes gases and liquids recovered from organic waste. (biomasse)

    calendar year

    calendar year[Repealed, SOR/2018-263, s. 1]

    capacity factor

    capacity factor, in respect of a unit in a calendar year, means the ratio of the quantity of electricity referred to in section 19 that is produced by the unit to the quantity of electricity that would be produced by the unit in the calendar year if it were to operate at its production capacity at all times during the calendar year. (facteur de capacité)

    coal

    coal includes petroleum coke and synthetic gas that is derived from coal or petroleum coke. (charbon)

    commissioning date

    commissioning date means

    • (a) for an electricity generator that began producing electricity by means of thermal energy using a fuel other than coal, and not in conjunction with coal, but that was converted into a unit before June 23, 2010, the day on which that generator began to produce electricity for sale to the electric grid using fuel other than coal, and not in conjunction with coal; and

    • (b) in any other case, the day on which a unit begins to produce electricity for sale to the electric grid. (date de mise en service)

    existing unit

    existing unit means a unit that is neither an old unit nor a new unit. (groupe existant)

    fossil fuel

    fossil fuel means a fuel other than biomass. (combustible fossile)

    front end engineering design study

    front end engineering design study means a collection of studies that provide the necessary details to support the carrying out of a construction project for the capture element of a carbon capture and storage system, including

    • (a) technical drawings and documents that describe the capture element in sufficient detail to permit the tendering of a contract for its construction;

    • (b) an estimation of the capital cost of the capture element with a margin of error of ± 20%;

    • (c) a safety review of the capture element;

    • (d) a risk assessment of the carbon capture and storage system, namely an assessment of the risks that may delay or prevent the completion of the construction of the system, including technical, economic, environmental, legal and labour-related risks;

    • (e) a strategy to mitigate those risks; and

    • (f) a detailed plan to carry out the construction of the carbon capture and storage system, including a schedule for the completion of its major steps. (étude d’ingénierie d’avant-projet détaillé)

    gasification system

    gasification system includes a gasification system that is in part located underground. (système de gazéification)

    GPA

    GPA means the Gas Processors Association of the United States. (GPA)

    major equipment

    major equipment means a boiler, gasifier, shift reactor, turbine, air pollution control device, air separation unit, compressor, CO2 separation system or other equipment that

    • (a) is manufactured in accordance with specifications in its purchase order and takes more than 12 months after the date of the purchase order to be manufactured and delivered; or

    • (b) costs $10,000,000 or more. (équipement majeur)

    new unit

    new unit means a unit, other than an old unit, whose commissioning date is on or after July 1, 2015. (groupe nouveau)

    old unit

    old unit means a unit that has reached the end of its useful life but continues to produce electricity. (groupe en fin de vie utile)

    operator

    operator means the person that operates or has the charge, management or control of a unit. (exploitant)

    power plant

    power plant means all units, buildings and other structures and all stationary equipment — including equipment for the separation and initial pressurization of CO2 of the capture element of a carbon capture and storage system — on a single site, or on adjacent sites that function as a single integrated site, whose primary purpose is the production of electricity for sale to the electric grid. (centrale électrique)

    production capacity

    production capacity, in relation to a unit and a calendar year, means

    • (a) the maximum continuous rating of the unit, expressed in MW, as most recently reported to a provincial authority of competent jurisdiction or to the electric system operator in the province where the unit is located; or

    • (b) if no report has been made, the most electricity that was produced for sale by the unit, expressed in MW, during two continuous hours in that calendar year. (capacité de production)

    Reference Method

    Reference Method means the document entitled Reference Method for Source Testing: Quantification of Carbon Dioxide Releases by Continuous Emission Monitoring Systems from Thermal Power Generation, June 2012, published by the Department of the Environment. (Méthode de référence)

    responsible person

    responsible person means an owner or operator of a unit. (personne responsable)

    standard m3

    standard m3 has the meaning assigned to a cubic metre at standard pressure and standard temperature by the definition standard volume in subsection 2(1) of the Electricity and Gas Inspection Regulations. (m3 normalisé)

    standby unit

    standby unit means an old unit that, for a given calendar year, operates at a capacity factor of 9% or less. (groupe de réserve)

    unit

    unit means physically connected equipment located in a power plant — including boilers and other combustion devices, gasifiers, reactors, turbines, generators and emission control devices — that operates together to produce electricity by means of thermal energy using coal as a fuel, whether in conjunction with other fuels or not. (groupe)

    useful life

    useful life, in respect of a unit, means the period that begins on the commissioning date and ends on

    • (a) for a unit other than a unit referred to in paragraph (a) of the definition commissioning date,

      • (i) in the case of a unit whose commissioning date is before 1975, the earlier of

        • (A) December 31 of the calendar year that is 50 years after the commissioning date, and

        • (B) December 31, 2019, and

      • (ii) in the case of a unit whose commissioning date is after 1974, the earlier of

        • (A) December 31 of the calendar year that is 50 years after the commissioning date, and

        • (B) December 31, 2029; and

    • (b) for a unit referred to in paragraph (a) of the definition commissioning date, 18 months after the applicable date described in paragraph (a). (vie utile)

  • Marginal note:Interpretation of incorporated documents

    (2) For the purposes of interpreting documents incorporated by reference into these Regulations, “should” must be read to mean “must” and any recommendation or suggestion must be read as an obligation.

  • Marginal note:Standards incorporated by reference

    (3) Any standard of the ASTM or GPA that is incorporated by reference into these Regulations is incorporated as amended from time to time.

  • SOR/2018-263, s. 1