Metal and Diamond Mining Effluent Regulations
Version of section 10 from 2006-03-22 to 2018-05-31:
10 (1) The owner or operator of a mine shall submit in writing to the authorization officer the information required by section 9, for
(a) any final discharge point that is identified by an inspector, and that was not identified as required by section 9, within 30 days after the discharge point is identified; and
(b) each new final discharge point, at least 60 days before depositing effluent from that new final discharge point.
(2) The owner or operator shall submit in writing to the authorization officer the information on any proposed change to a final discharge point at least 60 days before the change is to be made.