Metal and Diamond Mining Effluent Regulations
Version of section 24 from 2018-06-01 to 2024-11-26:
24 (1) The owner or operator of a mine shall notify an inspector without delay if the results of the effluent monitoring tests conducted under section 12 or 13, subsection 14(1) or section 15 or 16 indicate that
(a) the limits set out in Schedule 4 are being or have been exceeded;
(b) the pH of the effluent is less than 6.0 or greater than 9.5; or
(c) an effluent is acutely lethal.
(2) The owner or operator shall provide a written report of the test results to the inspector within 30 days after the tests have been completed.
(3) [Repealed, SOR/2018-99, s. 23]
- SOR/2006-239, s. 12
- SOR/2018-99, s. 23
- Date modified: