Energy Efficiency Regulations, 2016

Version of section 214.1 from 2025-04-09 to 2025-10-08:


Marginal note:Transitional provision — early compliance

 A split system central heat pump that is manufactured on or after January 1, 2025 and before January 1, 2026 is deemed to satisfy the requirements of sections 213 and 214 of these Regulations if it satisfies the requirements of sections 213 and 214 of the new Regulations that are applicable to split system central heat pumps that are manufactured on or after January 1, 2026.

  • SOR/2025-110, s. 40