7 The Board may order a company to submit to the Board within a specified period a design, specification, program, manual, procedure, measure, plan or document if
(a) the company makes an application to the Board under Part III or V of the Act; or
(b) the Board receives any information that the design, construction, operation or abandonment of the company’s processing plant, or a part of it, is or may cause
(i) a detriment to property or to the environment; or
(ii) a hazard to the safety of persons.