Marginal note:Deadline for decision
72 (1) Unless the individual grievance relates to classification, the person whose decision constitutes the appropriate level of the individual grievance process must provide the decision to the grievor or the grievor’s representative, if any, no later than 20 days after the day on which the individual grievance was received by the grievor’s immediate supervisor or the grievor’s local officer-in-charge identified under subsection 65(1).
Marginal note:Exception
(2) If the individual grievance relates to classification, the deadline is 80 days.