International Bridges and Tunnels Regulations

Version of section 9 from 2009-02-18 to 2012-03-13:

  •  (1) An owner of an international bridge or international tunnel shall ensure that the report referred to in section 8 contains at least the following information:

    • (a) the date of the inspection;

    • (b) the names of the persons who conducted the inspection;

    • (c) the elements of the international bridge or international tunnel that were inspected;

    • (d) in the case of an international tunnel, a list of the electrical, communication, mechanical and plumbing systems that were inspected;

    • (e) the utilities and their supports whose damage would have an impact on the safety of the international bridge or international tunnel;

    • (f) recommendations in respect of maintenance and repair projects, including recommendations as to when such projects must be completed and a list of maintenance work to be carried out;

    • (g) a list of inspections to be conducted following the inspection in respect of which the report is prepared, and a recommendation as to when those inspections must be completed;

    • (h) the maintenance work, major repairs and other work completed in respect of the bridge since the previous inspection report; and

    • (i) the special condition surveys, tests and other additional engineering investigations into the condition of the international bridge or international tunnel completed since the previous inspection report.

  • (2) The owner shall ensure that the report is accompanied by a letter signed and sealed by two engineers, one of whom is the team leader, attesting to the correctness of the information in the report and providing a statement as to the overall condition of the structure.