Marginal note:Requirements
10 A responsible person who has been granted a temporary exemption in respect of a unit under subsection 9(3) must satisfy the following requirements:
(a) carry out a front end engineering design study is to be carried out by January 1, 2020;
(b) purchase any major equipment that is necessary for the capture element is to be purchased by January 1, 2021;
(c) enter into any contract required for the transportation and storage of CO2 emissions from the unit is to be entered into by January 1, 2022;
(d) take all necessary steps to obtain all permits or approvals required in relation to the construction of the capture element are to be taken by January 1, 2022; and
(e) ensure that the unit, when operating with an integrated carbon capture and storage system, captures CO2 emissions from the combustion of fossil fuels in the unit in accordance with the laws of Canada or a province that regulate that capture and transports and stores those emissions in accordance with the laws of Canada or a province, or of the United States or one of its states, that regulate that transportation or storage, as the case may be, by January 1, 2024.