Marginal note:Excavation
17 An excavation in respect of which a person has obtained the pipeline company’s written permission under paragraph 6(b) of the National Energy Board Pipeline Crossing Regulations, Part I prior to June 19, 2016 is an authorized ground disturbance under subsection 112(1) of the National Energy Board Act, as it reads on June 19, 2016, and the measures to be taken in relation to the excavation are those set out in section 6 of those Regulations as it read immediately before the day on which these Regulations come into force.
- SOR/2019-349, s. 7