National Energy Board Cost Recovery Regulations (SOR/91-7)
Full Document:
- HTMLFull Document: National Energy Board Cost Recovery Regulations (Accessibility Buttons available) |
- XMLFull Document: National Energy Board Cost Recovery Regulations [79 KB] |
- PDFFull Document: National Energy Board Cost Recovery Regulations [231 KB]
Regulations are current to 2024-10-30 and last amended on 2011-01-01. Previous Versions
14 (1) The cost recovery charge payable by a large oil pipeline company is equal to the amount determined by the formula
A x B/C
where
- A
- is the total amount of costs determined in accordance with subsection 13(1);
- B
- is the forecast of deliveries, in cubic metres, of that company for the following year provided to the Board pursuant to paragraph 10(1)(a); and
- C
- is the aggregate of the forecasts of deliveries, in cubic metres, for the following year, of all the large oil pipeline companies, provided to the Board pursuant to paragraph 10(1)(a).
(2) The cost recovery charge payable by a large gas pipeline company is equal to the amount determined by the formula
A x B/C
where
- A
- is the total amount of costs determined in accordance with subsection 13(2);
- B
- is the forecast of deliveries, in cubic metres, of that company for the following year provided to the Board pursuant to paragraph 10(1)(a); and
- C
- is the aggregate of the forecasts of deliveries, in cubic metres, for the following year, of all the large gas pipeline companies, provided to the Board pursuant to paragraph 10(1)(a).
(3) The cost recovery charge payable by a large power line company is equal to the amount determined by the formula
A × B/C
where
- A
- is the total amount of costs determined in accordance with subsection 13(3);
- B
- is the forecast of electricity transmissions, in megawatt hours, of that company for the following year, provided to the Board under paragraph 10(2)(a); and
- C
- is the aggregate of the forecasts of electricity transmissions, in megawatt hours, of all the large power line companies for the following year, provided to the Board under paragraph 10(2)(a).
(4) [Repealed, SOR/2009-307, s. 14]
- SOR/98-267, s. 7
- SOR/2009-307, s. 14
- Date modified: