  •  (1) A holder of a transitional authorization in respect of a wastewater system must, during the period of authorization,

    • (a) comply with sections 7 to 10, 12 to 14, 16 to 22 and 48; and

    • (b) respect the plan referred to in, as the case may be, subsection 4(1) or paragraph 25(1)(f) and, if applicable, paragraph 25(1)(s) — or, if applicable, that plan as approved with changes under subsection 27(2) — and respect its schedule for implementation.

  • Marginal note:Progress reports

    (2) The holder of a transitional authorization must, within 90 days before the following dates, send to the authorization officer a progress report on the steps taken to implement the plan referred to in, as the case may be, subsection 4(1) or paragraph 25(1)(f) and, if applicable, paragraph 25(1)(s) — or, if applicable, that plan as approved with changes under subsection 27(2):

    • (a) July 1, 2017, if the period of authorization ends on December 31, 2020;

    • (b) July 1, 2020 and July 1, 2025, if the period of authorization ends on December 31, 2030; and

    • (c) July 1, 2020, July 1, 2025, July 1, 2030 and July 1, 2035, if the period of authorization ends on December 31, 2040.