  1. Information and Management of Time Limits Regulations - SOR/2019-283 (SCHEDULE 2 : Information Required in Detailed Description of Designated Project)

    [...]

    PART B

    Planning Phase Results

    • [...]

    • 5 Any study or plan, relevant to the project, that is being or has been conducted in respect of the region where the project is to be carried out, including a regional assessment that is being or has been carried out under section 92 or 93 of the Act or by any jurisdiction, including by or on behalf of an Indigenous governing body, if the study or plan is available to the public.

  2. Information and Management of Time Limits Regulations - SOR/2019-283 (SCHEDULE 1 : Information Required in Initial Description of Designated Project)

    [...]

    PART A

    General Information

    • [...]

    • 5 Any study or plan, relevant to the project, that is being or has been conducted in respect of the region where the project is to be carried out, including a regional assessment that is being or has been carried out under section 92 or 93 of the Act or by any jurisdiction, including by or on behalf of an Indigenous governing body, if the study or plan is available to the public.

  3. Information and Management of Time Limits Regulations - SOR/2019-283 (Section 5)

     For the purposes of paragraph 18(1)(b) of the Act, the Agency must provide the proponent with the following documents:

    • (a) tailored guidelines regarding the information or studies referred to in paragraph 18(1)(a) of the Act;


  4. Information and Management of Time Limits Regulations - SOR/2019-283 (Section 2)

     For the purposes of any of subsections 9(5), 18(5), 28(9), 36(3) and 37(6) of the Act, a time limit may be suspended in respect of the following activities and in the following circumstances:

    • [...]

    • (b) the undertaking of studies or the collection of information by the proponent related to a change in the design, construction or operation plans for a designated project and the resulting effects of the change, if the Agency or the review panel, as the case may be, is of the opinion that the change would alter the potential effects of the project and there is not sufficient information available to it for the purpose of conducting the impact assessment or preparing the impact assessment report; and


  5. Information and Management of Time Limits Regulations - SOR/2019-283 (Section 5)

    [...]

     For the purposes of paragraph 18(1)(b) of the Act, the Agency must provide the proponent with the following documents:

    • [...]

      (a) tailored guidelines regarding the information or studies referred to in paragraph 18(1)(a) of the Act;