Marginal note:Construction — facility
272 (1) A person must not construct an international or interprovincial power line that passes on, over, along or under a facility unless a permit referred to in section 248, or a certificate, has been issued in respect of the power line and
(a) the permit or certificate contains a condition relating to that facility;
(b) the person has been granted leave under subsection (2); or
(c) the person is constructing the power line in circumstances specified in an order or regulation made under subsection (4).
Marginal note:Authority to grant leave
(2) On application, the Commission may, by order, grant a person leave to construct an international or interprovincial power line that passes on, over, along or under a facility. It may require from the applicant any plans, profiles and other information that it considers necessary to consider the application.
Marginal note:Conditions
(3) The leave may be granted in whole or in part and be subject to conditions.
Marginal note:Circumstances
(4) The Regulator may specify circumstances for the purposes of paragraph (1)(c) by regulation, and the Commission may do so by order.
Marginal note:Leave in emergency cases
(5) The Commission may grant leave under subsection (2) after construction of the work has commenced if it is satisfied that the work was urgently required and, before the commencement of construction, it was notified of the person’s intention to proceed with the work.