Marginal note:Reasons
63 (1) The Commission must issue written reasons for each decision or order it makes. A designated officer must do the same for each decision or order they make.
Marginal note:Public availability
(2) The Regulator must make the decisions and orders, and the reasons for them, publicly available.
Marginal note:Non-application
(3) This section does not apply to a decision or order that is made only in relation to the internal administrative affairs of the Regulator.