Mackenzie Valley Resource Management Act
Marginal note:Transboundary effects
140 (1) Where it appears to the Review Board, during the environmental assessment of a development proposed to be carried out wholly within the Mackenzie Valley, that the development might have a significant adverse impact on the environment in a region outside the Mackenzie Valley, the Review Board shall so advise the authority responsible for the examination of environmental effects in that region and request its cooperation in the conduct of the assessment.
Marginal note:Agreement — other authority
(2) Where the Review Board has determined that a development referred to in subsection (1), other than a development that has been referred to the Minister of the Environment under paragraph 130(1)(c), is likely to have a significant adverse impact on the environment in a region outside the Mackenzie Valley, the Review Board may, with the approval of the federal Minister, enter into an agreement with the authority responsible for the examination of environmental effects in that region to provide for
(a) the coordination of the respective examinations of the environmental impact of the development; or
(b) the examination of the environmental impact of the development by a joint panel established for that purpose.
Marginal note:Time limit
(2.1) Any agreement under paragraph (2)(b) shall be entered into within three months after the day on which the Review Board is advised, as the case may be,
(a) of an order for an environmental impact review under subparagraph 130(1)(b)(ii) or paragraph 131(1)(b); or
(b) in accordance with subsection 130(4.07), that the proposal has not been referred to the Minister of the Environment.
Marginal note:Extension of time limit by federal Minister
(2.2) The federal Minister may, at the request of the Review Board, extend the time limit referred to in subsection (2.1) by a maximum of two months to take into account circumstances that are specific to the proposal.
Marginal note:Extension of time limit by Governor in Council
(2.3) The Governor in Council may, on the recommendation of the federal Minister, further extend the time limit extended under subsection (2.2) any number of times.
Marginal note:Excluded period
(2.4) If the Review Board requires the person or body that proposes to carry out the development to provide information, or collect information or undertake a study with respect to the development, then the period that is taken by that person or body, in the Review Board’s opinion, to comply with the requirement is not included in the calculation of the time limit under subsection (2.1) or of its extension.
Marginal note:Environmental impact review
(2.5) Despite subsections (2.1) to (2.4), if, within the time limit set out in those subsections, an agreement has not been entered into under paragraph (2)(b), a panel of the Review Board shall conduct an environmental impact review of the development.
Marginal note:Joint panel’s report
(3) Within 15 months after the day on which a joint panel is established under paragraph (2)(b), the panel shall make a report of its recommendations to
(a) the federal Minister, who shall distribute it to every responsible minister;
(b) any designated regulatory agency from which a licence, permit or other authorization is required for the carrying out of the development; and
(c) the Tlicho Government, if the development is to be carried out wholly or partly on Tlicho lands.
Marginal note:Extension of time limit by federal Minister
(3.1) The federal Minister may, at the request of the joint panel, extend the time limit referred to in subsection (3) by a maximum of two months to take into account circumstances that are specific to the proposal.
Marginal note:Extension of time limit by Governor in Council
(3.2) The Governor in Council may, on the recommendation of the federal Minister, further extend the time limit extended under subsection (3.1) any number of times.
Marginal note:Excluded period
(3.3) If the joint panel requires the person or body that proposes to carry out the development to provide information, or collect information or undertake a study with respect to the development, then the period that is taken by that person or body, in the joint panel’s opinion, to comply with the requirement is not included in the calculation of the time limit under subsection (3) or of its extension.
Marginal note:Provisions applicable
(4) An examination by a joint panel established under subsection (2) stands in lieu of an environmental impact review of the proposal and paragraphs 134(1)(b), (d) and (e) and sections 135 to 137.2 apply, with such modifications as may be required, in respect of the examination, except that a recommendation of a panel may not be referred back to the panel for further consideration.