Government of Canada / Gouvernement du Canada
Symbol of the Government of Canada

Search

Canadian Energy Regulator Processing Plant Regulations

Version of section 43 from 2020-03-16 to 2024-10-30:

  •  (1) If a company proposes to reactivate a processing plant or part of one that has been deactivated for 12 months or more, the company shall notify the Regulator of that fact before the reactivation.

  • (2) The company shall set out in the notification the reasons, and the procedures that are to be used, for the reactivation.

  • SOR/2008-270, s. 2
  • SOR/2020-50, s. 36

Date modified: