Canadian Energy Regulator Onshore Pipeline Regulations
6.1 (1) A company shall establish, implement and maintain a management system that
(a) is explicit, comprehensive and proactive;
(b) integrates the company’s operational activities and technical systems with its management of human and financial resources;
(c) applies to all the company’s activities involving the design, construction, operation or abandonment of a pipeline and to the programs referred to in section 55;
(d) ensures coordination between the programs referred to in section 55; and
(e) corresponds to the size of the company, to the scope, nature and complexity of its activities and to the hazards and risks associated with those activities.
(2) A company shall establish its management system within 90 days after the day on which the certificate or order authorizing it to construct or operate a pipeline is issued under the Act.