Marginal note:Review

  •  (1) On receipt of a request made under section 125, the Commission must conduct the review or cause the review to be conducted by a person designated under subsection 116(1.1).

  • Marginal note:Restriction

    (2) The Commission must conduct the review if the notice of violation was issued by a person designated under subsection 116(1.1).