Marginal note:Impact Assessment Act

 If an application under section 298 relates to a designated project, as defined in section 2 of the Impact Assessment Act, that is subject to an impact assessment under that Act,

  • (a) despite the time limit established under subsections 298(4) and (5), the Commission must make its decision under subsection 298(4) within seven days after the day on which the decision statement with respect to the project is posted on the Internet under section 66 of that Act;

  • (b) the Commission must make its decision under subsection 298(4) solely on the basis of the report referred to in paragraph 51(1)(d) of that Act; and

  • (c) subsections 298(3) and (6) to (8) do not apply with respect to the application.