Canadian Energy Regulator Act (S.C. 2019, c. 28, s. 10)
Full Document:
- HTMLFull Document: Canadian Energy Regulator Act (Accessibility Buttons available) |
- XMLFull Document: Canadian Energy Regulator Act [820 KB] |
- PDFFull Document: Canadian Energy Regulator Act [1356 KB]
Act current to 2026-06-17 and last amended on 2026-03-26. Previous Versions
Marginal note:Impact Assessment Act
299 If an application under section 298 relates to a designated project, as defined in section 2 of the Impact Assessment Act, that is subject to an impact assessment under that Act,
(a) despite the time limit established under subsections 298(4) and (5), the Commission must make its decision under subsection 298(4) within seven days after the day on which the decision statement with respect to the project is posted on the Internet under section 66 of that Act;
(b) the Commission must make its decision under subsection 298(4) solely on the basis of the report referred to in paragraph 51(1)(d) of that Act; and
(c) subsections 298(3) and (6) to (8) do not apply with respect to the application.