Marginal note:Duty to pay

  •  (1) A subcontractor that is paid by a contractor under subsection 10(1) must, no later than the 42nd day after the day on which the proper invoice is received by Her Majesty or the service provider, pay each of its subcontractors for the construction work that they invoiced and that was covered by the proper invoice and paid for by Her Majesty or the service provider.

  • Marginal note:Partial payment

    (2) For the purpose of subsection (1), if the subcontractor is only paid in part, it must distribute the amount received from the contractor in the following manner:

    • (a) on a rateable basis, the subcontractor must pay any of its subcontractors whose construction work is not covered by a notice of non-payment provided under subsection 10(3) and may retain any amount owed to the subcontractor by the contractor for any of the subcontractor’s own construction work that is not covered by such a notice; and

    • (b) then, from any remaining amount and on a rateable basis, the subcontractor must pay any of its subcontractors whose work is partly covered by the notice of non-payment provided under subsection 10(3) and may retain any amount owed to the subcontractor by the contractor for any of the subcontractor’s own construction work that is partly covered by such a notice.

  • Marginal note:Non-payment

    (3) Despite subsection (1), the subcontractor may decline to pay for some or all of the construction work if, no later than the 35th day after the day on which the proper invoice is received, the subcontractor provides its subcontractor with a notice of non-payment.

  • Marginal note:Further application — subcontracting chain

    (4) This section applies to any other subcontractor in the subcontracting chain, with any necessary modifications, so that

    • (a) any subcontractor that is paid under subsection (1) must pay its subcontractors no later than the 49th day after the day on which the proper invoice is received by Her Majesty or the service provider and those subcontractors must pay any of their subcontractors no later than the 56th day after the day on which the proper invoice is received and so on, in increments of seven days, until the end of the subcontracting chain; and

    • (b) any subcontractor that is paid under subsection (1) may decline to pay any of its subcontractors if it provides them with a notice of non-payment no later than the 42nd day after the day on which the proper invoice is received by Her Majesty or the service provider and those subcontractors may decline to pay any of their subcontractors if they provide them with a notice of non-payment no later than the 49th day after the day on which the proper invoice is received and so on, in increments of seven days, until the end of the subcontracting chain.