Cross-border Movement of Hazardous Waste and Hazardous Recyclable Material Regulations (SOR/2021-25)
Full Document:
- HTMLFull Document: Cross-border Movement of Hazardous Waste and Hazardous Recyclable Material Regulations (Accessibility Buttons available) |
- XMLFull Document: Cross-border Movement of Hazardous Waste and Hazardous Recyclable Material Regulations [785 KB] |
- PDFFull Document: Cross-border Movement of Hazardous Waste and Hazardous Recyclable Material Regulations [1280 KB]
Regulations are current to 2024-10-30 and last amended on 2021-10-31. Previous Versions
PART 1Import, Export and Transit (continued)
DIVISION 1Import (continued)
Import Permit (continued)
Marginal note:Refusal to issue permit
9 The Minister must refuse to issue a permit if
(a) an authorization referred to in subparagraph 185(1)(b)(i) of the Act is not obtained, unless the circumstances in subsection 185(4) of the Act apply;
(b) the Minister has reasonable grounds to believe that, if the permit were issued, the movement of hazardous waste or hazardous recyclable material, or the disposal of hazardous waste or recycling of hazardous recyclable material, under the permit would not comply with the Act, these Regulations or conditions to an authorization imposed by the jurisdiction of destination or a country of transit; or
(c) the Minister has reasonable grounds to believe that false or misleading information was provided in the notification under section 8.
Marginal note:Period of validity of permit
10 A permit is valid for the period set out in it, which cannot be longer than
(a) 36 months after the day on which it is issued, in the case of hazardous recyclable material
(i) that is to be imported from a country of origin that is subject to OECD Decision C(2001)107/FINAL and, if applicable, conveyed in transit only through a country that is subject to that Decision, and
(ii) that is to be recycled by means of a final recycling operation at a receiving facility that is a pre-consented recovery facility referred to in Case 2 in Chapter II. D (2) of OECD Decision C(2001)107/FINAL, as amended from time to time, to the extent that the amendments are binding on Canada; and
(b) 12 months after the day on which it is issued, in any other case.
Marginal note:New application
11 If a permit needs to be amended the permit holder must apply for a new permit.
Marginal note:Suspension of permit required
12 (1) The Minister must suspend a permit if an authority referred to in subparagraph 185(1)(b)(i) of the Act withdraws an authorization referred to in that subparagraph.
Marginal note:Optional suspension of permit
(2) The Minister may suspend a permit if the Minister has reasonable grounds to believe that
(a) the permit holder no longer satisfies the conditions in section 7;
(b) the movement of hazardous waste or hazardous recyclable material, or the disposal of hazardous waste or recycling of hazardous recyclable material, under the permit does not comply — or will not comply — with the Act, these Regulations or the conditions of an authorization imposed by the jurisdiction of destination or a country of transit;
(c) false or misleading information was provided in the notification under section 8;
(d) as a result of a natural or artificial disaster or another emergency, the movement of hazardous waste or hazardous recyclable material, or the disposal of hazardous waste or recycling of hazardous recyclable material, cannot be in accordance with the permit; or
(e) the hazardous waste or hazardous recyclable material is not being managed in a manner that will protect the environment and human health against the adverse effects that may result from it.
Marginal note:Notice
(3) The Minister must notify the permit holder of the suspension, the reasons for it and the period during which it applies.
Marginal note:Manner of notice
(4) The Minister notifies the permit holder when the Minister
(a) informs the permit holder at their last known address or email address that the notice of the suspension and the reasons for it are available through a generally accessible electronic source and identifies the location of the notice and reasons; or
(b) sends the notice and reasons to the permit holder’s last known address or email address.
Marginal note:Representations
(5) The permit holder may make written representations to the Minister as to why the permit should be reinstated within the period of the suspension.
Marginal note:Reinstatement of permit
(6) The Minister may reinstate the permit only if the matter that gave rise to the suspension has been resolved or corrected during the period of the suspension.
Marginal note:Revocation of permit
13 (1) The Minister must revoke a permit if the matter that gave rise to a suspension has not been resolved or corrected within the period of suspension or if the permit holder requests the revocation.
Marginal note:Notice
(2) Before revoking a permit, the Minister must notify the permit holder of the proposed revocation and the reasons for it.
Marginal note:Manner of notice
(3) The Minister notifies the permit holder when the Minister
(a) informs the permit holder at their last known address or email address that the notice of the proposed revocation and the reasons for it are available through a generally accessible electronic source and identifies the location of the notice and reasons; or
(b) sends the notice and reasons to the permit holder’s last known address or email address.
Marginal note:Representations
(4) The permit holder may make written representations to the Minister as to why the permit should not be revoked.
Marginal note:Date of revocation
(5) The revocation of a permit is not effective until 20 days after the day on which the Minister notifies the permit holder.
Conditions Under Paragraph 185(1)(c) of the Act
Conditions Relating to Import
Marginal note:Conditions
14 (1) For the purposes of paragraph 185(1)(c) of the Act, the prescribed conditions for the import of hazardous waste or hazardous recyclable material under one or more permits that are held by a permit holder are the following:
(a) the movement, and the disposal or recycling, of the hazardous waste or hazardous recyclable material must be in accordance with the permit or permits;
(b) the import must not be prohibited under the laws of Canada;
(c) the country of origin must be a party to the Convention or the Canada-USA Agreement or must be subject to OECD Decision C(2001)107/FINAL and the export of the hazardous waste or hazardous recyclable material must not be prohibited by that country;
(d) the conveyance in transit of the hazardous waste or hazardous recyclable material through a country must not be prohibited by that country;
(e) biomedical waste set out in item 1 of Schedule 6 or anything that meets the criteria for inclusion in Class 6.2 as set out in Part 2 of the Transportation of Dangerous Goods Regulations must be disposed of by means of a final disposal operation;
(f) if anything contains PCBs in a concentration greater than 50 mg per kg, the PCBs in that thing or in any residue from its decontamination must be destroyed or irreversibly transformed;
(g) the permit holder and all authorized carriers that transport the hazardous waste or hazardous recyclable material in Canada must hold the liability insurance referred to in Division 7 of this Part;
(h) all of the contracts referred to in paragraphs 8(4)(c) to (e) must be in effect;
(i) every contract referred to in paragraph 8(4)(c) must
(i) describe each type of hazardous waste or hazardous recyclable material that is to be imported under the contract,
(ii) set out the quantity of each type of hazardous waste or hazardous recyclable material,
(iii) identify the operation set out in column 2 of Part 1 or 2 of Schedule 1 that is to be performed on each type of hazardous waste or hazardous recyclable material,
(iv) state that the hazardous waste or hazardous recyclable material is to be imported in accordance with the permit, and
(v) require the foreign exporter and the facility to take all feasible measures to assist the permit holder to satisfy the conditions under paragraph 185(1)(c) of the Act;
(j) every contract referred to in paragraphs 8(4)(d) and (e) must
(i) describe each type of hazardous waste or hazardous recyclable material that is to be imported under the contract,
(ii) set out the quantity of each type of hazardous waste that is to be disposed of, or hazardous recyclable material that is to be recycled, at the authorized facility,
(iii) identify the operation set out in column 2 of Part 1 or 2 of Schedule 1 that is to be performed on each type of hazardous waste or hazardous recyclable material at the authorized facility,
(iv) state that the hazardous waste is to be disposed of, or the hazardous recyclable material is to be recycled, in accordance with the permit,
(v) require the authorized facility to notify the permit holder in writing, within 30 days after the day on which the authorized facility completes an interim or final disposal operation for a type of hazardous waste, or an interim or final recycling operation for a type of hazardous recyclable material, that is recorded as a line entry in the movement document,
(A) of the date on which the operation was completed,
(B) of the reference number of the movement document, and the line number of the line entry in the movement document, that applies to that type of hazardous waste or hazardous recyclable material, and
(C) that the operation was completed in a manner that protects the environment and human health against the adverse effects that may result from the hazardous waste or hazardous recyclable material, and
(vi) require the authorized facility to take all feasible measures to assist the permit holder to satisfy the conditions under paragraph 185(1)(c) of the Act;
(k) every contract referred to in paragraph 8(4)(e) must require the receiving facility to provide the authorized facility that is to dispose of a type of hazardous waste or recycle a type of hazardous recyclable material that was contained in the shipment by means of a final disposal operation or final recycling operation with the reference number of the movement document and the line number of the line entry in the movement document that applies to that type of hazardous waste or hazardous recyclable material;
(l) each shipment must be recorded in a separate movement document in accordance with sections 15 and 16;
(m) the movement document completed in accordance with section 16 must be provided, in accordance with that section, to the Minister and the authorities of the province where the receiving facility is located;
(n) while they transport the shipment, every authorized carrier must produce the permit or permits, and Parts A and B of the movement document completed in accordance with section 16, when they are required to do so to demonstrate that the movement of the shipment complies with this Division;
(o) the permit or permits, and Parts A and B of the movement document completed in accordance with section 16, must be provided to a customs office when the hazardous waste or hazardous recyclable material that is contained in the shipment is required to be reported at the customs office under section 12 of the Customs Act;
(p) if the receiving facility is to dispose of a type of hazardous waste or recycle a type of hazardous recyclable material under the permit or permits by means of an interim disposal operation or interim recycling operation, it must complete the disposal of all of the hazardous waste, or the recycling of all of the hazardous recyclable material, of that type that is contained in a shipment, either within a period of 180 days after the day on which the shipment is delivered to it or within a shorter period required by the authorities of the jurisdiction in which it is located;
(q) if the receiving facility is to dispose of a type of hazardous waste or recycle a type of hazardous recyclable material under the permit or permits by means of a final disposal operation or final recycling operation, it must complete the disposal of all of the hazardous waste, or the recycling of all of the hazardous recyclable material, of that type that is contained in a shipment, either within a period of one year after the day on which the shipment is delivered to it or within a shorter period required by the authorities of the jurisdiction in which it is located;
(r) if an authorized facility other than a receiving facility is to dispose of a type of hazardous waste or recycle a type of hazardous recyclable material under the permit or permits by means of a final disposal operation or final recycling operation, it must complete the disposal of all of the hazardous waste, or the recycling of all of the hazardous recyclable material, of that type that was contained in a shipment delivered to the receiving facility and that was sent to the authorized facility by the receiving facility, either within a period of 18 months after the day on which the shipment was delivered to the receiving facility or within a shorter period required by the authorities of the jurisdiction in which the authorized facility is located;
(s) the Minister must be provided with confirmation of the disposal of the hazardous waste by means of an operation set out in column 2 of Part 1 of Schedule 1, or of the recycling of the hazardous recyclable material by means of an operation set out in column 2 of Part 2 of Schedule 1, in accordance with section 17;
(t) the documents referred to in section 18 must be kept in accordance with that section;
(u) if the permit holder is notified that the receiving facility does not accept hazardous waste or hazardous recyclable material that is contained in a shipment that is shipped in accordance with the Act and these Regulations, or that it cannot, or refuses to, dispose of that hazardous waste or recycle that hazardous recyclable material in accordance with the permit,
(i) the permit holder must immediately notify the Minister and the foreign exporter of the situation and the reason for it,
(ii) if necessary, the permit holder must store the hazardous waste or hazardous recyclable material in a facility that is authorized for that purpose by the authorities of the jurisdiction in which the facility is located,
(iii) within 90 days after the day on which the Minister is notified or within any other period of time that is agreed to by the Minister and the competent authority of the country of origin, the permit holder must either
(A) make all necessary arrangements to dispose of the hazardous waste by means of a final disposal operation, or to recycle the hazardous recyclable material by means of a final recycling operation, at another authorized facility in Canada and provide the Minister with the name and address of, and the name of a contact person for, that authorized facility, the reference number of the movement document and, for each type of hazardous waste or hazardous recyclable material, the line number of the applicable line entry in the movement document, the quantity in kilograms or litres and the applicable disposal or recycling code set out in column 1 of either Part 1 or 2 of Schedule 1, or
(B) in accordance with Division 6 of this Part, return the hazardous waste or hazardous recyclable material to the country of origin under an export permit for the return,
(iv) the hazardous waste or hazardous recyclable material must not be transported to an authorized facility referred to in clause (iii)(A) unless the permit holder has received confirmation from the Minister that the authorities of the jurisdiction in which the authorized facility is located have approved its disposal or recycling at that authorized facility, and
(v) if the hazardous waste or hazardous recyclable material is transported to an authorized facility referred to in clause (iii)(A) for disposal or recycling, the authorized facility must complete the disposal of all of the hazardous waste by means of a final disposal operation, or the recycling of all of the hazardous recyclable material by means of a final recycling operation, within one year after the expiry of the period referred to in subparagraph (iii); and
(v) if a shipment is imported in accordance with the Act and these Regulations but the Minister notifies the permit holder that the Minister does not accept hazardous waste or hazardous recyclable material that is contained in the shipment or that hazardous waste or hazardous recyclable material that is contained in the shipment cannot be moved, disposed of or recycled in accordance with the permit,
(i) the permit holder must immediately notify the foreign exporter of the situation and the reason for it,
(ii) if necessary, the permit holder must store the hazardous waste or hazardous recyclable material in a facility that is identified for that purpose by the Minister,
(iii) within 90 days after the day on which the Minister notifies the permit holder or within any other period of time that is agreed to by the Minister and the competent authority of the country of origin, the permit holder must either
(A) make all necessary arrangements to dispose of the hazardous waste by means of a final disposal operation, or to recycle the hazardous recyclable material by means of a final recycling operation, at an authorized facility in Canada and provide the Minister with the name and address of, and the name of a contact person for, that authorized facility, the reference number of the movement document and, for each type of hazardous waste or hazardous recyclable material, the line number of the applicable line entry in the movement document, the quantity in kilograms or litres and the applicable disposal or recycling code set out in column 1 of either Part 1 or 2 of Schedule 1, or
(B) in accordance with Division 6 of this Part, return the hazardous waste or hazardous recyclable material to the country of origin under an export permit for the return,
(iv) the hazardous waste or hazardous recyclable material must not be transported to an authorized facility referred to in clause (iii)(A) unless the permit holder has received confirmation from the Minister that the authorities of the jurisdiction in which the authorized facility is located have approved its disposal or recycling at that authorized facility, and
(v) if the hazardous waste or hazardous recyclable material is transported to an authorized facility referred to in clause (iii)(A) for disposal or recycling, the authorized facility must complete the disposal of all of the hazardous waste by means of a final disposal operation, or the recycling of all of the hazardous recyclable material by means of a final recycling operation, within one year after the expiry of the period referred to in subparagraph (iii).
Marginal note:Delivery to receiving facility
(2) For the purposes of paragraphs (1)(p) to (r), delivery of a shipment to the receiving facility occurs when the shipment arrives at the receiving facility, regardless of whether or when hazardous waste or hazardous recyclable material that is contained in the shipment is accepted by the receiving facility.
Marginal note:Necessary arrangements
(3) The necessary arrangements referred to in clauses (1)(u)(iii)(A) and (v)(iii)(A) must include a requirement that the authorized facility notify the permit holder in writing, within 30 days after the day on which the authorized facility completes a final disposal operation for a type of hazardous waste, or a final recycling operation for a type of hazardous recyclable material, that is recorded as a line entry in the movement document,
(a) of the date on which the operation was completed;
(b) of the reference number of the movement document, and the line number of the line entry in the movement document, that applies to that type of hazardous waste or hazardous recyclable material; and
(c) that the operation was completed in a manner that protects the environment and human health against the adverse effects that may result from the hazardous waste or hazardous recyclable material.
Marginal note:Manner of notice
(4) For the purposes of subparagraph (1)(v)(iii), the Minister notifies the permit holder when the Minister
(a) informs the permit holder at their last known address or email address that the notice is available through a generally accessible electronic source and identifies the location of the notice; or
(b) sends the notice to the permit holder’s last known address or email address.